Arroyo and San Rafael Undergrounding Project - Updated 11/5/2013

Project Description
Project Schedule and Traffic Advisory - Please see revised closure schedule!
Construction Boundaries and Map 


 San Rafael Bridge 

Description:

Before the City of Pasadena can complete the La Loma Road Bridge Rehabilitation project, the electrical system needs to be set underground on the following streets:

  • Arroyo Boulevard from Madeline Drive to San Rafael Avenue
  • San Rafael Avenue from Arroyo Boulevard to Laguna Road.

Perry Thomas Construction Inc. was awarded the contract to complete this project by City Council approval on October 7, 2013

Schedule and Traffic Advisory:

Road Closed SignConstruction will begin on Monday, October 28, 2013 and is scheduled to be completed in January 31, 2014.

No construction will occur during the City's Holiday Moratorium, from December 15th to January 8th. 

The San Rafael Bridge is expected to be closed weekdays from 9am to 3pm for a total of three weeks from November 11 to November 27.

 

Construction Boundaries and Map:

The map below outlines the construction boundaries on Arroyo Boulevard and San Rafael Avenue:

Rafael Construction Map 

 

Notice of Construction 

 